Construction Update September 28, 2023

Access Update

The contractor is currently working on storm sewer and road grading near the intersection of 2nd Ave and 10th St NW. Green Prairie facilities, Plainview Senior Housing and 8th St NW must be accessed from the East until further notice. Emergency services have been notified.
As construction in this area progresses east, access will be modified once again. Please watch for additional updates early next week.
________________________________________
Contact Us 
If you have any questions, please contact Sawyer Hander at 507-226-3472 or Drew Weber at 507-469-0306. For further information about this project, visit the project website.